Morse Arena
UMaine Facility Location
University of Maine, Orono
Project Summary
Completion of construction is anticipated by the Fall of 2027. Funded in part with a lead investment from the Harold Alfond Foundation as part of UMS TRANSFORMS, a historic $320M initiative designed to shape the future of higher education in Maine. This transformational commitment brings revolutionary change to the state’s largest educational, research, innovation, and talent development asset. As the final phase of the Athletics Facilities Master Plan, Morse Arena will provide support to maintain excellence in the state’s only Division I athletics program.
Skip Chappelle Court at Morse Arena
The new home of Maine Basketball will combine the intimate feeling of “The Pit” with a comfortable and convenient arena where fans can enjoy games and our teams will have an unrivaled home court advantage. Over 2,600 seats nestled below a full concourse and club section will provide an enhanced in-game experience. Chairback seats with excellent, clear views of the court and extra amenities, along with easy access to concessions and restrooms, will be the new normal at Black Bear basketball games. Preferred seating with access to a new club will provide Maine fans with a true premium ticket experience. In addition, a newly created student-section tradition will increase the gameday experience along with high-definition video boards, quality audio and impressive Maine branding throughout the facility.
Football Operations Center
A key feature of Morse Arena is the Football Operations Center to support Maine Football. This will include coaches’ offices, a conference room, and staff meeting spaces. The new facility will also offer an area inside the new club space large enough to allow full team gatherings. Maine Football will have a dedicated entrance and corridor leading to the team offices and the Walt Abbott Sports Performance Center. Newly designed spaces combined with modern technology will allow our coaches to teach and train student-athletes in an enhanced setting.
General Info
Facility Function: Athletics
Current Phase: Construction
Status: In-Progress
Project Type: New Space
Facility Name: Morse Arena
College or Division: Athletics
Gross Square Feet: 75,000
Project / Design Start Date: 2024
Construction Start: Fall 2025
Occupancy Date: Early 2028
Project Architect: WBRC Inc. and Crawford Architects
General Contractor: Consigli
Project Manager: Robert Spence, UMS CPPM
Campus FM Lead: Joshua Burke, UM FM Space & Capital Management Services
Budget Info
Total Project Budget: $106 million
Funding Sources: Harold Alfond Foundation, Phillip and Susan Morse, Others