Black Bear Academy
UMaine Facility Location
Old Town, Maine
Project Summary
The Black Bear Academy project expands childcare capacity at UMaine while modernizing existing facilities to meet current standards. The initiative will increase the number of available childcare slots to better support students, faculty, staff and the surrounding community.
This project reflects a broader commitment to strengthening campus infrastructure and addressing critical workforce and family needs. By enhancing access to high-quality childcare, the university supports retention, recruitment and overall campus well-being. Located on the edge of campus, the facilities improve accessibility for both university affiliates and local families, reinforcing UMaine’s role as a community partner.
In addition to expanding capacity, the project will align facilities with updated health, safety and accessibility expectations established since the pandemic.
General Info
Facility Function: Support
Current Phase: Design
Status: In-Progress
Project Type: Space Renewal, Safety, Code
College or Division: Auxiliary Services
Gross Square Feet: 130,000
Project / Design Start Date: Winter 2025
Construction Start: Season Spring 2026
Occupancy Date: Season Fall 2026
Project Architect: Harriman
General Contractor: Penobscot General Contractors
Project Manager: Logan Doucette, UMS CPPM
Campus Facilities Management Lead: Dana Underwood, UM FM Space & Capital Management Services
Budget Info
Total Project Budget: $4 million
Funding Sources: Congressionally Delegated Spending secured by Sens. Susan Collins and Angus King