  • Annual snow removal training for campus crews is Tuesday. First snow of this season in Orono is expected on Wednesday.
  • Roof repair at D.P. Corbett Business Building is expected to start on Wednesday.
  • Sod being installed at the Advanced Structures and Composites Center Thursday, weather permitting.
  • Terrell House window and siding installation should be completed this week.
  • Final campus paving projects campuswide being scheduled.
  • Carpet replacement in the Collins Center for the Arts scheduled for winter break.
  • Ongoing: Holmes and Coburn halls construction;  Aquaculture Research Center demolition; construction of experimental blueberry beds at Wyman’s Wild Blueberry Research and Innovation Center.